FL-5.1.4 (K3) Use estimation techniques to calculate the required test effort
5. The team wants to estimate the time needed for one tester to execute four test cases for a software component. The team has gathered the following measures of the effort used to execute a single test case:
Best-case scenario: 1 hour
Worst-case scenario: 8 hours
Most likely scenario: 3 hours
Given that the three-point estimation technique is being used, what is the final estimate of the time needed to execute all four test cases ?