5.2 Risk Management

FL-5.2.4 (K2) Explain what measures can be taken in response to analyzed product risks

        1. During a risk analysis the following risk was identified and assessed:

  • Risk: Response time is too long to generate a report
  • Risk likelihood: medium; risk impact: high
  • Response to risk:

                  o An independent test team performs performance testing during system testing

                   o A selected sample of end users performs alpha and beta acceptance testing before the release

What measure is proposed to be taken in response to this analyzed risk ?

a)  Risk acceptance        

b)  Contingency plan               

c)  Risk mitigation                

d)  Risk transfer  

Answer Explanation