5.3 Test Monitoring, Test Control and Test Completion

FL-5.3.3 (K2) Exemplify how to communicate the status of testing

        1. Which tool can be used by an agile team to show the amount of work that has been completed and the amount of total work remaining for a given iteration ?

a)  Acceptance criteria            

b)  Defect report   

c)  Test completion report        

d)  Burndown chart     

Answer Explanation