5.1 Test Planning

FL-5.1.4 (K3) Use estimation techniques to calculate the required test effort

        1. Your team uses the three-point estimation technique to estimate the test effort for a new high-risk feature. The following estimates were made :

  • Most optimistic estimation: 2 person-hours
  • Most likely estimation: 11 person-hours
  • Most pessimistic estimation: 14 person-hours

    What is the final estimate ?

a)  9 person-hours          

b)  14 person-hours          

c)  11 person-hours   

d) 10 person-hours 

Answer Explanation