FL-5.1.4 (K3) Use estimation techniques to calculate the required test effort
3. You want to estimate the test effort for the new project using estimation based on ratios. You calculate the test-to-development effort ratio using averaged data for both development effort and test effort from four historical projects similar to the new one. The table shows this historical data .
Project
Development effort ($)
Test effort ($)
P1
800,000
40,000
P2
1,200,000
130,000
P3
600,000
70,000
P4
1,000,000
120,000