5.2 Risk Management

FL-5.2.1 (K1) Identify risk level by using risk likelihood and risk impact

        2. For a given risk, its risk level is $1,000 and its risk likelihood is estimated as 50%.

What is the risk impact ?

a)  $500                 

b)  $2,000                

c)  $50,000            

d)  $200  

Answer Explanation