i . Management moves two experienced testers to another project
ii . The system does not comply with functional safety standards
iii . System response time exceeds user requirements
iv . Stakeholders have inaccurate expectations
v . Disabled people have problems when using the system
a) i, iv are project risks
b) iv, v are project risks
c) i, iii are project risks
d) ii, v are project risks
Answer Explanation