5.2 Risk Management

FL-5.2.2 (K2) Distinguish between project risks and product risks

        2. Which of the following are product risks?

a)  Scope creep                   

b)  Poor architecture                 

c)  Cost-cutting              

d)  Poor tool support 

e)  Response time too long 

Answer Explanation