5.1 Test Planning

FL-5.1.4 (K3) Use estimation techniques to calculate the required test effort

        4. At the beginning of each iteration, the team estimates the amount of work (in person-days) they will need to complete during the iteration. Let E(n) be the estimated amount of work for iteration n, and let A(n) be the actual amount of work done in iteration n. From the third iteration, the team uses the following estimation model based on extrapolation .

The graph shows the estimated and actual amount of work for the first four iterations

What is the estimated amount of work for iteration #5 ?

a)  10.5 person-days           

b)  8.25 person-days           

c)  6.5 person-days     

d) 9.4 person-days  

Answer Explanation